Fuel meter installation

1, the fuel flow meter installed flange connection, threaded connections and clamp-on;
2, the installation of the flow direction should be consistent with the sensor housing indicates the fuel meters direction of the arrow, and the straight pipe upstream should ≥6DS, downstream straight pipe should ≥5DS (DS was measured for the pipe diameter).
3, the sensor should be away from external magnetic field, if not avoided, should take the necessary measures;
4, in order not to affect the maintenance of normal transmission fluid should be installed bypass pipe on the outer ends of the sensor straight pipe
5, when the sensor outdoor installation, please do waterproof processing amplifier plugs;
6, sensor and display instrumentation wiring, should be selected according to the amplifier power supply wiring.